摘要: |
以普光气田至上海的天然气管道建设工程为背景,探讨了投产工艺在天然气长输管道投产中的实际应用。通过对采用"气推气"方式的天然气置换工艺、分阶段接替升压等投产方式进行技术分析,结合川气东送实际,更好地指导今后的输气管道投产工作。 |
关键词: 川气东送 长输管道 气推气 置换工艺 |
DOI: |
分类号:TE832 |
基金项目: |
|
Discuss of Long-Distance Natural Gas Pipeline Commissioning Processes from Sichuan to Eastern China Gas Transmission Pipeline Project |
Zhang Qingyong
|
SINOPEC Sichuan to Eastern China Gas Transmission Pipeline Company
|
Abstract: |
Taking the natural gas pipeline construction project from Puguang gas field to Shanghai as an example,this article discusses the actual application of the long-distance natural gas pipeline commissioning processes. By technical analysis of the natural gas replacement process of "Gas-to-Gas Process"and boosting by phases commissioning mode,combining the case of Sichuan to East gas transmission,it can provide better guide for future pipeline commissioning. |
Key words: Siehuan to East gas transmission long-distance pipeline gas-to-gas process replacementprocess |