摘要: |
热力除氧设施在延安石油化工厂120×104 t/a连续重整装置上的成功应用,解决了连续重整装置预加氢反应器压降大的技术瓶颈,避免了预加氢反应器频繁换剂、撇头,为装置的平稳长周期运行奠定了坚实的基础 |
关键词: 热力除氧 连续重整 压降 预加氢 |
DOI: |
分类号: |
基金项目: |
|
Application of thermal deaeration installation in the CCR unit |
Guo Feng, Wu Zhongli, Tian Jinguang, Zhang Lili
|
Yan’an Petrochemical Works, Yan’an 727406, Shaanxi, China
|
Abstract: |
The thermal deaeration installation is successfully applied on the 1200×103 t/a CCR unit of Yan’an Petrochemical Works. The technical bottleneck of the higher pressure drop of the pre-hydrogenation reactor of continuous reforming unit is solved, the frequently replacement and skimming of the catalyst of pre- hydrogenation unit are avoided,which can effectively ensure the smooth and long- term operation of the equipment. |
Key words: thermal deaeration installation, CCR,pressure drop, pre-hydrogenation |